The temporary road to the Golf Practice Facility has been completed.
The Bank Stabilization Contractor has relocated his construction boxes to the southern portion of the site.
The Contractor is continuing grading operations on the site, and has completed temporary sediment basin 1. Temporary sediment basins 2a and 2b are nearly complete. The contractor is currently grading the majority of the north end of the site.